Sunday, August 5, 2018

Finishing


7/28/18 - Started fitting the front windshield and top. Total time = 8 hours.

Fitting the Windshield & Top
8/11/18 - Finished painting rudder, rudder fairing, doors, root skins and door trim pieces. Total time = 3 hours.

Final Items Painted Before Installing
8/12/18 - Installing the root skins on top of the fuselage. Total time = 8 hours.

Riveting the Root Skins on Top of the Fuselage
8/17/18 - Installing the top panel and front windshield to the fuselage. Total time = 8 hours.
Riveting the Top Panel



Top Panel and Front Windshield Installed
8/18/18 - Installed the vortex generators on the underside of the horizontal stabilizer.
Total time = 2 hours.

Vortex Generators Riveted in Place
8/19/18 - Fabricated and installed Oil Cooler Transition Piece for air opening on cowling. Total time = 2 hours.

Transition Piece Fabricated & Installed for Oil Cooller
8/26/18 - Drilled a hole in the top cowling over the air cleaner intake and epoxied an air intake scoop for forced air to enhance engine performance. Total time =  6 hours.

Air Scoop Epoxied to Top Cowling for Forced Air Intake
9/1/18 - Finished riveting top cowling to fastener hinge and added removal pins to left & right side of cowling. Total time = 5 hours.

Riveting Completed on Top Cowling
9/15/18 - Finished painting the cowling and then fitted the propeller with the spinner to get an idea of the final fit. I then did a weight and balance on the airplane. Total time = 5 hours.

Final Fit of the Cowling, Propeller & Spinner
9/22/18 - I didn't like the balance of the fiberglass spinner on the front of the propeller so I changed it for an aluminum spinner which also gave extra cooling to the reduction drive assembly. Total time = 2 hours. 
Aluminum Spinner Installed
9/29/18 - Applied vinyl graphic decals to the fuselage that I purchased off the internet. Total time = 3 hours. 
Adding Vinyl Graphics to the Fuselage
9/30/18 - Applied the "N" number to the tail along with the vinyl graphics. Total time = 1 hour.
"N" Number Added
9/30/18 - The Plane is Finished!  Total Finishing Time = 53 Hours.


The Finished Product
Total Airplane Construction Time = 1550 Hours.


10/04/18 - Traveled to Buzz Flight Academy in Tennessee to get some transition training in their Zenith CH 750.

Transition Training
11/14/18 - Received the Airworthiness Certificate and the Repairman's Certificate from the FAA. Let the flying begin!
Another Milestone is Achieved

1/06/19 - First Flight Completed







No comments:

Post a Comment