10/8/16 - Prepared the rudder cables by using the cable lug crimping tool to form the connection for the cables. Total time = 4 hrs.
Crimping the End of the Cable. |
10/15/16 - Prepared the rudder flange by drilling holes in the mounting bracket on the rudder. Total time = 2 hours.
Rudder Mounting Bracket |
10/29/16 - Installed rudder assembly onto the tail of the fuselage. Total time = 6 hrs.
Rudder attached to Fuselage Tail |
11/12/16 - Rudder stops were installed on the left & right side of the fuselage. Total time = 4 hours.
Rudder Stops Installed |
11/19/16 - Safety wire installed on the cable turnbuckles. Total time = 4 hours.
Safety Wire Installed |
4/1/17 - Prepared and installed the elevator cables on the inside of the fuselage. Total time = 6 hours.
Elevator Cables Hooked Up. |
4/2/17 - Safety wires were installed on the elevator cable turnbuckles. Total time = 3 hrs.
Elevator Cables Safety Wired. |
4/8/17 - Rudder cables attached to the rudder pedals. Total time = 2 hours.
Rudder Cables Connected to Rudders. |
4/15/17 - Elevator fairing attached to the top of the fuselage. Total time = 2 hrs.
Fairing Attached to Top of Fuselage |
4/22/17 - Elevator trim motor access panel installed on the underside of the elevator. Total time = 2 hours.
Elevator Trim Motor Access Panel Installed 4/29/17 |
4/29/17 - Elevator inspection panels installed. Total time = 4 hours.
Tightening Cover |
Inspection Panel |
Inspection Panel |